Specialized Vehicle Replacement
Federal contribution
$3.4M
$3,420,000
Federal share40%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2020
today
2021202320252027
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Oakville
- Construction start
- Aug 3, 2020(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start9 months earlyforecast Apr 30, 2021
Also in Oakville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56912 in the federal list. How to read these figures.