Conventional Vehicle Replacement - 2023
Federal contribution
$3.3M
$3,264,000
Federal share40%
of $8.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2020
today
2021202320252027
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Oakville
- Construction start
- Jun 1, 2024(actual)
- Construction end
- Dec 31, 2026(forecast)
Also in Oakville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56917 in the federal list. How to read these figures.