Renewal and expansion of the Oakville Transit Facility
Federal contribution
$14.8M
$14,794,968
Federal share33%
of $45.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Oakville
- Construction start
- Feb 10, 2010(actual)
- Construction end
- Apr 4, 2011(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Apr 1, 2010
- Construction end7 months earlyforecast Oct 31, 2011
Also in Oakville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32441 in the federal list. How to read these figures.