Conventional Vehicle Replacement - 2022

Oakville, Ontario

completePublic TransitPTIS
Federal contribution
$4.3M
$4,321,959
Federal share40%

of $10.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2020
20212022202320242025
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
Town of Oakville
Construction start
Oct 31, 2022(actual)
Construction end
Nov 29, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 30, 2022
  • Construction end2 months lateforecast Sep 30, 2024

Also in Oakville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56916 in the federal list. How to read these figures.