Amherst Island Culvert Replacement
Federal contribution
$111,000
Federal share33%
of $333.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Loyalist
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 7, 2010
- Construction end7 weeks lateforecast Aug 30, 2010
Also in Loyalist
- Construction of a Sustainable Community Hub in Loyalist Township - Retrofit$16.6M
- Hyland and Briscoe Rehabilitation$913.8K
- Detailed design and construction - Water main relining on Cambridge Crescent$302.1K
- Installation of stormwater infrastructure on Davy Street$255.7K
- Installation of stormwater infrastructure and water and sewer main replacement on Frink Avenue$175.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32076 in the federal list. How to read these figures.