Medicine Hat Family Leisure Centre Expansion

Medicine Hat, Alberta

completeSportMIC
Federal contribution
$10.0M
$10,000,000
Federal share28%

of $36.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2013
20132014201520162017
Built

Approved 6 weeks after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
City of Medicine Hat
Construction start
Aug 18, 2014(actual)
Construction end
Dec 16, 2016(actual)

Against the original forecast

  • Construction start15 months lateforecast Jun 1, 2013
  • Construction end6 months lateforecast Jun 30, 2016

Also in Medicine Hat

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32697 in the federal list. How to read these figures.