Rehabilitation of Highway 1
Federal contribution
$2.4M
$2,390,000
Federal share50%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Aug 26, 2010(actual)
- Construction end
- Jun 13, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 3, 2010
- Construction end2 weeks earlyforecast Jun 30, 2011
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40471 in the federal list. How to read these figures.