Medicine Hat Athletic Ball Park Upgrades
Federal contribution
$2.2M
$2,153,816
Federal share73%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2022
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Medicine Hat
- Construction start
- May 12, 2021(actual)
- Construction end
- Apr 15, 2022(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 1, 2021
- Construction end2 weeks lateforecast Mar 30, 2022
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58506 in the federal list. How to read these figures.