Schedule

Announced and approvedJun 26, 2024
today
202420252026202720282029
BuiltForecast

Approved 13 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Medicine Hat
Construction start
Jun 15, 2023(actual)
Construction end
Jul 1, 2029(forecast)

Against the original forecast

  • Construction start2 weeks earlyforecast Jul 1, 2023