Medicine Hat Pedestrian Bridge Deck Repair/Replacement
Federal contribution
$2.5M
$2,467,076
Federal share78%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2022
Built
Approved 2 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Medicine Hat
- Construction start
- May 1, 2021(actual)
- Construction end
- Sep 7, 2022(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Sep 30, 2022
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58476 in the federal list. How to read these figures.