Route 8 - Four Mile Brook to Five Mile Brook

Bathurst, New Brunswick

completeHighways and RoadsISF
Federal contribution
$600,000
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Jul 25, 2009(actual)
Construction end
Sep 14, 2009(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Oct 31, 2009