Valley Trail - Function Junction to Spring Creek
Federal contribution
$187,500
Federal share30%
of $615.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Whistler
- Construction start
- Sep 12, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2010
- Construction end3 weeks lateforecast Oct 10, 2011