Valley Trail - Function Junction to Spring Creek

Whistler, British Columbia

completeActive TransportationISF
Federal contribution
$187,500
Federal share30%

of $615.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Whistler
Construction start
Sep 12, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2010
  • Construction end3 weeks lateforecast Oct 10, 2011