Spo7ez Cultural Centre and Community Society - Squamish Lilwat Cultural Centre Facility Revitalization
Federal contribution
$1.5M
$1,471,719
Federal share75%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Spo7ez Cultural Centre and Community Society
- Construction start
- Feb 22, 2021(actual)
- Construction end
- Feb 28, 2025(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Apr 1, 2021
- Construction end4 weeks earlyforecast Mar 31, 2025
Also in Whistler