Emerald Water System Disinfection Upgrade
Federal contribution
$1.3M
$1,256,512
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Resort Municipality of Whistler
- Construction start
- Mar 26, 2018(actual)
- Construction end
- Feb 15, 2019(actual)
Against the original forecast
- Construction start16 months lateforecast Nov 15, 2016
- Construction end8 weeks lateforecast Dec 21, 2018