Emerald Water System Disinfection Upgrade

Whistler, British Columbia

completeDrinking WaterCWWF
Federal contribution
$1.3M
$1,256,512
Federal share50%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Mar 26, 2018(actual)
Construction end
Feb 15, 2019(actual)

Against the original forecast

  • Construction start16 months lateforecast Nov 15, 2016
  • Construction end8 weeks lateforecast Dec 21, 2018