Whistler CNG Fueling Facility
Federal contribution
$1.3M
$1,324,836
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 21, 2016
20172018
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- British Columbia Transit
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Dec 20, 2017(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 31, 2017
- Construction end3 months earlyforecast Mar 31, 2018
Also in Whistler
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47165 in the federal list. How to read these figures.