Whistler CNG Fueling Facility

Whistler, British Columbia

completePublic TransitPTIF
Federal contribution
$1.3M
$1,324,836
Federal share50%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 21, 2016
20172018
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
British Columbia Transit
Construction start
Jun 12, 2017(actual)
Construction end
Dec 20, 2017(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 31, 2017
  • Construction end3 months earlyforecast Mar 31, 2018

Also in Whistler

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47165 in the federal list. How to read these figures.