Highway 99 Resurfacing

Whistler, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.2M
$1,228,993
Federal share35%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 19, 2010
ApprovedSep 8, 2010
2011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 20, 2010(actual)
Construction end
Mar 1, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2010