Whistler - South Whistler Water Supply

Whistler, British Columbia

completeDrinking WaterGIS
Federal contribution
$2.4M
$2,447,283
Federal share40%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2023
202420252026
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 13, 2023(actual)
Construction end
Feb 10, 2026(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 27, 2023
  • Construction end6 weeks lateforecast Dec 31, 2025

Also in Whistler

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66916 in the federal list. How to read these figures.