Back to projects

Highway 104 Repaving

Colchester, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,440,000
Federal share50%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
2010
Built

Approved 3 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
May 28, 2010(actual)
Construction end
Aug 5, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2010

Also in Colchester

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35893 in the federal list. How to read these figures.