Colchester Active Transportation Connections
Federal contribution
$5.6M
$5,641,276
Federal share35%
of $16.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 9, 2026
today
202320242025202620272028
BuiltForecast
Approved 3.7 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of the County of Colchester
- Construction start
- Aug 2, 2023(actual)
- Construction end
- Mar 31, 2028(forecast)
Also in Colchester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64974 in the federal list. How to read these figures.