Debert Sewage Treatment Plant Expansion

Colchester, Nova Scotia

approvedWastewaterGIS
Federal contribution
$2.2M
$2,178,000
Federal share36%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2024
today
202320242025202620272028
BuiltForecast

Approved 15 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 1, 2026(forecast)
Construction end
Mar 31, 2028(forecast)

Also in Colchester