Debert Water Tower Replacement
Federal contribution
$954,661
Federal share24%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 28, 2015
ApprovedFeb 18, 2016
201620172018201920202021
Built
Approved 7 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Municipality of the County of Colchester
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Apr 30, 2021(actual)
Against the original forecast
- Construction start22 months lateforecast Sep 30, 2015
- Construction end4.3 years lateforecast Dec 30, 2016
Also in Colchester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45978 in the federal list. How to read these figures.