Central Nova Scotia Civic Centre
Federal contribution
$10.0M
$10,000,000
Federal share25%
of $40.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2011
201120122013
Built
Approved 10 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Municipality of the County of Colchester
- Construction start
- Sep 12, 2010(actual)
- Construction end
- Oct 21, 2013(actual)
Against the original forecast
- Construction end6 months lateforecast Apr 30, 2013
Also in Colchester