Arden Trunk Sewer
Federal contribution
$500,000
Federal share31%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedOct 16, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Courtenay
- Construction start
- May 17, 2010(actual)
- Construction end
- Sep 16, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2010
- Construction end3 months earlyforecast Dec 31, 2010
Also in Courtenay
- 6th Street Active Transportation Bridge in Courtenay, British Columbia$2.5M
- Courtenay - 17th Street Bike Lanes$1.4M
- East Courtenay Reservoir Twinning$1.3M
- Kus-kus-sum: Restoration of Estuarine Habitat to Re-establish Ecosystem Services and Build Coastal Resiliency$1.0M
- Rehabilitation of the 5th Street Bridge$982.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36754 in the federal list. How to read these figures.