Improvements to Duck Lake Road

Powell River, British Columbia

completeHighways and RoadsISF
Federal contribution
$90,000
Federal share47%

of $190.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
20102011
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 27, 2010(actual)
Construction end
Feb 28, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2010