Native Sons Hall

Courtenay, British Columbia

completeCultureISF
Federal contribution
$628,677
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Courtenay
Construction start
Nov 1, 2009(actual)
Construction end
Feb 28, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 1, 2009
  • Construction end4 weeks earlyforecast Mar 31, 2011

Also in Courtenay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39153 in the federal list. How to read these figures.