Native Sons Hall
Federal contribution
$628,677
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Courtenay
- Construction start
- Nov 1, 2009(actual)
- Construction end
- Feb 28, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 1, 2009
- Construction end4 weeks earlyforecast Mar 31, 2011
Also in Courtenay
- 6th Street Active Transportation Bridge in Courtenay, British Columbia$2.5M
- Courtenay - 17th Street Bike Lanes$1.4M
- East Courtenay Reservoir Twinning$1.3M
- Kus-kus-sum: Restoration of Estuarine Habitat to Re-establish Ecosystem Services and Build Coastal Resiliency$1.0M
- Rehabilitation of the 5th Street Bridge$982.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39153 in the federal list. How to read these figures.