Highway 1 - Oregan Jack, 1 Kilometre South of Junction Highway 97C

Ashcroft, British Columbia

completeHighways and RoadsISF
Federal contribution
$875,010
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 19, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Apr 1, 2010(actual)
Construction end
Jun 24, 2010(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast May 15, 2010
  • Construction end2 months earlyforecast Aug 27, 2010

Also in Ashcroft

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39394 in the federal list. How to read these figures.