Ashcroft - Hot Tub Replacement

Ashcroft, British Columbia

completeRecreationCCRIS
Federal contribution
$69,686
Federal share40%

of $174.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Village of Ashcroft
Construction start
Aug 1, 2022(actual)
Construction end
Jun 15, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Feb 28, 2022
  • Construction end6 months lateforecast Nov 30, 2022