Ashcroft Community Water Treatment Plant

Ashcroft, British Columbia

completeDrinking WaterSCF
Federal contribution
$2.9M
$2,862,678
Federal share33%

of $8.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620172018201920202021
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Ashcroft
Construction start
Jun 14, 2018(actual)
Construction end
Aug 16, 2021(actual)

Against the original forecast

  • Construction end7 months earlyforecast Mar 31, 2022