Village of Ashcroft 2016 Sewage Treatment Plant Upgrade Dewatering Centrifuge
Federal contribution
$265,000
Federal share50%
of $530.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Ashcroft
- Construction start
- Jul 24, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start15 months earlyforecast Oct 31, 2018
Also in Ashcroft
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49768 in the federal list. How to read these figures.