Ashcroft - Ashcroft Fire Department Hall Retrofit

Ashcroft, British Columbia

completeVentilationCVRIS
Federal contribution
$550,887
Federal share80%

of $688.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Ashcroft
Construction start
Feb 1, 2023(actual)
Construction end
Dec 20, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast Jun 30, 2022
  • Construction end3 weeks lateforecast Nov 30, 2023

Also in Ashcroft

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60395 in the federal list. How to read these figures.