Highway 1 Resurfacing
Federal contribution
$399,758
Federal share47%
of $850.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- May 25, 2010(actual)
- Construction end
- Sep 24, 2010(actual)
Against the original forecast
- Construction end6 months earlyforecast Mar 31, 2011
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39559 in the federal list. How to read these figures.