Highway 400 - Regional Road 88 Bridge Rehabilitation
Bradford West Gwillimbury, Ontario
Federal contribution
$200,000
Federal share50%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Nov 10, 2010(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Nov 30, 2010
Also in Bradford West Gwillimbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39651 in the federal list. How to read these figures.