St. Thomas Line Widening
Paradise, Newfoundland and Labrador
Federal contribution
$414,159
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20152016
Built
Approved 20 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Paradise
- Construction start
- Sep 1, 2015(actual)
- Construction end
- Mar 31, 2016(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2015
Also in Paradise
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45025 in the federal list. How to read these figures.