North Shore Wastewater Treatment Plant
North Vancouver, British Columbia
Federal contribution
$212.3M
$212,300,000
Federal share33%
of $636.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2016
today
201620192022202520282031
BuiltForecast
Approved 3 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Metro Vancouver
- Construction start
- Nov 1, 2019(actual)
- Construction end
- Aug 31, 2030(forecast)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2019