Highway 1 Lynn Creek Connectivity Improvement

North Vancouver, British Columbia

completeHighways and RoadsNRP
Federal contribution
$20.4M
$20,402,957
Federal share50%

of $40.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
2017201920212023
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 31, 2018(actual)
Construction end
Nov 28, 2022(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Sep 1, 2018
  • Construction end12 months lateforecast Nov 30, 2021

Also in North Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48184 in the federal list. How to read these figures.