Highway 1 - Mountain Highway Interchange
North Vancouver, British Columbia
Federal contribution
$12.5M
$12,500,000
Federal share50%
of $25.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedNov 12, 2014
ApprovedFeb 25, 2015
20152016201720182019
Built
Approved 3 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of British Columbia
- Construction start
- May 1, 2017(actual)
- Construction end
- Oct 1, 2019(actual)
Against the original forecast
- Construction start12 months lateforecast May 1, 2016
- Construction end4 months lateforecast Jun 15, 2019
Also in North Vancouver
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45819 in the federal list. How to read these figures.