Back to projects

Highway 1 - Mountain Highway Interchange

North Vancouver, British Columbia

completeHighways and RoadsMIC
Federal contribution
$12.5M
$12,500,000
Federal share50%

of $25.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedNov 12, 2014
ApprovedFeb 25, 2015
20152016201720182019
Built

Approved 3 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
May 1, 2017(actual)
Construction end
Oct 1, 2019(actual)

Against the original forecast

  • Construction start12 months lateforecast May 1, 2016
  • Construction end4 months lateforecast Jun 15, 2019

Also in North Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45819 in the federal list. How to read these figures.