Highway 1 Lower Lynn Corridor Improvement
North Vancouver, British Columbia
Federal contribution
$20.9M
$20,915,060
Federal share50%
of $41.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 17, 2015
ApprovedJan 13, 2016
2016201820202022
Built
Approved 9 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of British Columbia
- Construction start
- Jul 31, 2018(actual)
- Construction end
- Oct 31, 2021(actual)
Also in North Vancouver
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45816 in the federal list. How to read these figures.