Bus facilities and exchanges

North Vancouver, British Columbia

completePublic TransitPTIF
Federal contribution
$18.2M
$18,219,706
Federal share50%

of $36.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2016
2017201820192020
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
Metro Vancouver
Construction start
Jan 15, 2019(actual)
Construction end
Jun 20, 2020(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jan 1, 2019
  • Construction end9 months earlyforecast Mar 31, 2021