Arrow Mainline and Erickson Open Reservoir Replacement Phase 4
Central Kootenay, British Columbia
Federal contribution
$1.5M
$1,460,651
Federal share33%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2015
20162017
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Regional District of Central Kootenay
- Construction start
- May 17, 2016(actual)
- Construction end
- Nov 10, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2016
- Construction end3 months lateforecast Jul 28, 2017
Also in Central Kootenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46090 in the federal list. How to read these figures.