Arrow Mainline and Erickson Open Reservoir Replacement – Phase 4

Central Kootenay, British Columbia

completeDrinking WaterSCF
Federal contribution
$1.5M
$1,460,651
Federal share33%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2015
20162017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 17, 2016(actual)
Construction end
Nov 10, 2017(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2016
  • Construction end3 months lateforecast Jul 28, 2017

Also in Central Kootenay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46090 in the federal list. How to read these figures.