Upper Gar Creek Water

Central Kootenay, British Columbia

completeDisaster MitigationSCF
Federal contribution
$97,432
Federal share33%

of $292.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
20182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 10, 2017(actual)
Construction end
Aug 31, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 17, 2017
  • Construction end9 months lateforecast Nov 30, 2018