Regional District of Central Kootenay - East Shore Connectivity

Central Kootenay, British Columbia

completeBroadband And ConnectivityRNIS
Federal contribution
$469,200
Federal share60%

of $782.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022202320242025
Built

Approved 6 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 11, 2021(actual)
Construction end
Sep 29, 2025(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 16, 2021
  • Construction end6 months lateforecast Mar 28, 2025