Regional District of Central Kootenay - East Shore Connectivity
Central Kootenay, British Columbia
Federal contribution
$469,200
Federal share60%
of $782.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022202320242025
Built
Approved 6 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Regional District of Central Kootenay
- Construction start
- May 11, 2021(actual)
- Construction end
- Sep 29, 2025(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 16, 2021
- Construction end6 months lateforecast Mar 28, 2025
Also in Central Kootenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56345 in the federal list. How to read these figures.