Central Kootenay - Woodbury Village Water System Treatment Upgrade
Central Kootenay, British Columbia
Federal contribution
$288,504
Federal share60%
of $480.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021202220232024
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Regional District of Central Kootenay
- Construction start
- Apr 24, 2023(actual)
- Construction end
- Jan 1, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Dec 1, 2022
- Construction end5 weeks lateforecast Nov 30, 2023
Also in Central Kootenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56203 in the federal list. How to read these figures.