Castlegar - Nelson Active Transportation Corridor Vision, BC

Central Kootenay, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
20232024
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Construction start
Mar 13, 2023(actual)
Construction end
Aug 15, 2024(actual)

Against the original forecast

  • Construction start9 months lateforecast Jun 1, 2022
  • Construction end2 months lateforecast May 31, 2024

Also in Central Kootenay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64381 in the federal list. How to read these figures.