Emergency Access Road Re-Development
Federal contribution
$101,435
Federal share31%
of $330.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2015
20162017
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Nigigoonsiminikaaning First Nation
- Construction start
- May 15, 2017(actual)
- Construction end
- Jul 4, 2017(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 31, 2017
- Construction end6 weeks earlyforecast Aug 18, 2017
Also in Fort Frances
- Rainycrest Long Term Care Home - HVAC Upgrades and Replacement$2.3M
- Revitalization of the Fort Frances Memorial Sports Centre$2.0M
- Rainycrest LTC Sprinkler System$1.6M
- Construction of Fort Frances Public Library and Technology Centre$955.0K
- Reconstruction of Colonization Road East from Scott Street intersection to just north of 5th Street Intersection$948.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46237 in the federal list. How to read these figures.