Emergency Access Road Re-Development

Fort Frances, Ontario

completeDisaster MitigationSCF
Federal contribution
$101,435
Federal share31%

of $330.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2015
20162017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 15, 2017(actual)
Construction end
Jul 4, 2017(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 31, 2017
  • Construction end6 weeks earlyforecast Aug 18, 2017

Also in Fort Frances

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46237 in the federal list. How to read these figures.