Back to projects

Sewer Tanks, Pump and Line Repairs/Replacement

Fort Frances, Ontario

completeWastewaterSCF
Federal contribution
$38,919
Federal share32%

of $123.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20162017
Built

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Naicatchewenin First Nation
Construction start
Oct 7, 2016(actual)
Construction end
Sep 30, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2016
  • Construction end4 months lateforecast Jun 15, 2017

Also in Fort Frances