Water and Sewer Extension
Summerford, Newfoundland and Labrador
Federal contribution
$259,594
Federal share33%
of $793.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2016
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Summerford
- Construction start
- May 16, 2016(actual)
- Construction end
- Oct 17, 2016(actual)
Against the original forecast
- Construction end12 months earlyforecast Oct 31, 2017
Also in Summerford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46677 in the federal list. How to read these figures.