Strongs Island W&S Phase 2

Summerford, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$807,841
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
2023202420252026
Built

Approved 3.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Summerford
Construction start
Apr 29, 2024(actual)
Construction end
Jul 10, 2025(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 1, 2024
  • Construction end7 months lateforecast Dec 20, 2024