Strongs Island W&S Phase 2
Summerford, Newfoundland and Labrador
Federal contribution
$807,841
Federal share40%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
2023202420252026
Built
Approved 3.5 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Summerford
- Construction start
- Apr 29, 2024(actual)
- Construction end
- Jul 10, 2025(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 1, 2024
- Construction end7 months lateforecast Dec 20, 2024
Also in Summerford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65144 in the federal list. How to read these figures.