Back to projects

Trokes Road & Wharf Loop Water and Sewer Upgrades

Summerford, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$274,581
Federal share39%

of $705.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Summerford
Construction start
Jun 26, 2023(actual)
Construction end
Oct 13, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2023
  • Construction end2 months earlyforecast Dec 13, 2023

Also in Summerford