Daniel's Road Water Main Upgrades

Summerford, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$153,999
Federal share40%

of $385.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Summerford
Construction start
Oct 8, 2020(actual)
Construction end
Jul 30, 2021(actual)

Against the original forecast

  • Construction start2 months earlyforecast Dec 10, 2020
  • Construction end20 months earlyforecast Mar 31, 2023