Lift Station Retrofit - Summerford
Summerford, Newfoundland and Labrador
Federal contribution
$97,575
Federal share40%
of $243.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Summerford
- Construction start
- Nov 7, 2023(actual)
- Construction end
- Jul 10, 2024(actual)
Against the original forecast
- Construction start3 months earlyforecast Feb 15, 2024
- Construction end8 weeks lateforecast May 15, 2024
Also in Summerford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61120 in the federal list. How to read these figures.